top of page

Agencies Please Don't Make the Same Mistake Six Times

Writer's picture: Dick Lieberman,ConsultantDick Lieberman,Consultant

A case at the Armed Services Board of Contract Appeals appears to demonstrate that some contract administrators never seem to learn, and repeated the same mistake 6 times while administering a contract for construction of an unmanned aircraft facility at Creech Air Force Base, NV. See Jaynes Corp., ASBCA No. 58385, May 7, 2013 (entitlement) and Jaynes Corp., ASBCA No. 59234, May 19, 2015 (quantum, awarding the contractor 96% of his $56,305 claim, plus interest).

These cases involve the pipes to be used in the building’s sprinkler system. When Jaynes submitted its required shop drawings, equipment data, and material samples prior to starting, it proposed an Allied (subcontractor) sprinkler system, with piping identified as “Allied Sched 40 ASTM A135/A795.” ASTM is an international standards organization frequently used for government specifications, and formerly was the American Society for Testing and Materials (“ASTM”). The Administrative Contracting Officer (“ACO”) disapproved the Allied piping submission, asserting that the piping did not comply with Sched 40/A795, but only complied with ASTM Sched 10, and was “not real Sched 40 pipe,” it is just an Allied “trade name.” Jaynes made the submittal six times and was rejected each time, on

  • December 2, 2011;

  • February 2, 2012;

  • April 10, 2012;

  • May 3, 2012, ;

  • May 4, 2012; and

  • May 8, 2012

The May 4, 2012 submittal included an affidavit from the Metallurgy Manager of Allied, the subcontractor, explaining in detail why the pipe complied with the specification. The affidavit noted that the affiant was a committee member of ASTM 109.09 as well as the sponsor of the ASTM A135 Pipe Standard. It didn’t matter, the ACO disapproved it anyway, and Jaynes was required to replace the rejected piping with acceptable pipe, thereby giving rise to Jaynes’s $56,305 claim.

In its entitlement decision, the Board concluded that the contract required Schedule 40, ASTM A135 or A795 pipe. The Board noted that the government (the ACO”) had dismissed Jaynes’ explanation of the proper interpretation “without any principled analysis of its own.” The ACO had no factual basis for rejecting the Allied pipe, and never rebutted the Allied Manager’s affidavit, or a second affidavit from Southland Industries’ Chief Design Officer, which concurred that the pipe complied. The Board concluded that the Government had changed the contract when it rejected the Allied pipe submittal, and sustained Jaynes’s claim.

Two years later, in ASBCA No. 59234, the Government attempted to deny the claim again through the calculation of entitlement. It asserted that since the Government had rejected the Allied pipe before Jaynes purchased it, Jaynes “caused its own damage.” The Board, however, rejected this argument as “absurd,” noting that the Government never had the right to reject Allied pipe that was “fully in conformance with contract requirements…The government was consistently and persistently wrong and we will not shift the fault to appellant.” The only adjustment the Board made to the claim was to give the Government credit for the salvage value of the Allied pipe that Jaynes retained, reducing the entitlement by $1,295.

TIPS: Government personnel must apply reason, common sense and fairness in all aspects of government contracts. Indeed, the Federal Acquisition Regulation (“FAR”) explicitly states that the acquisition system will “conduct business with integrity, fairness and openness.” FAR 1.102(b)(3). Was this FAR requirement met by the ACO in this case? If a contractor’s submittals do not appear to comply with the contract, and additional support is offered (especially expert support), the Contracting Officer must carefully consider that support. Only when the information supplied by the contractor is factually wrong—and the ACO can demonstrate it—can a submittal of the type in this case be rejected. And, after being confronted with the information six times, the Government should have regrouped and reconsidered, and only rejected the pipe if the evidence was clear—which it was not.

Visit our other site, “Richard D. Lieberman’s FAR Consulting & Training,” for other government contracting articles at https://www.richarddlieberman.com/


8 views0 comments

Recent Posts

See All

Use Caution with Rubber Stamps

Is a rubber stamped signature of the President of a company on a release of claims valid? The Civilian Board of Contract Appeals, under...

Comentarios


This website was developed by Richard Lieberman, a government contracts consultant and retired attorney who is the author of both "The 100 Worst Mistakes in Government Contracting" (with Jason Morgan) and "The 100 Worst Government Mistakes in Government Contracting." Richard Lieberman concentrates on Federal Acquisition Regulation (FAR) consulting and training, including  commercial item contracting (FAR Part 12), compliance with proposal requirements(FAR Part 15 negotiated procurement), sealed bidding (FAR Part 14), compliance with solicitation requirements, contract administration (FAR Part 42), contract modifications and changes (FAR Part 43), subcontracting and flowdown requirements (FAR Part 44), government property (FAR Part 45), quality assurance (FAR Part 46), obtaining invoiced payments owed to contractors,  and other compliance with the FAR.   See LinkedIn profile at https://www.linkedin.com/in/richard-d-lieberman-3a25257a/.This website and blog are for educational and information purposes only.  Nothing posted on this website constitutes legal advice, which can only be obtained from a qualified attorney. Website Owner/Consultant does not engage in the practice of law and will not provide legal advice or legal services based on competence and standing in the law. Legal filings and other aspects of a legal practice must be performed by an appropriate attorney. Using this website does not establish an attorney-client relationship. Although the author strives to present accurate information, the information provided on this site is not guaranteed to be complete, correct or up-to-date.  The views expressed on this blog are solely those of the author. FAR Consulting & Training, Tel. 202-520-5780, rliebermanconsultant@gmail.com

Copyright © 2020 Richard D. Lieberman

bottom of page